Major Projects Executed

  DESIGN, SUPPLY OF MATERIAL AND CONSTRUCTION OF FLOW LINES AND ASSOCIATED WORKS FOR OIL WELLS AT GC-27 AND GC-28  
  ENGINEERING, PROCUREMENT AND CONSTRUCTION OF STEAM SYSTEM REVAMP PROJECT (SSRP) AT MINA ABDULLA REFINERY  
  FUEL OIL SUPPLY PROJECT (FOSP)  
  DESIGN, DETAIL ENGINEERING AND CONSTRUCTION OF AHMADI DEPOT AND MODERNIZATION OF SABHAN DEPOT
  DESIGN, MANUFACTURE, SUPPLY, INSTALLATION AND COMMISSIONING OF EMERGENCY GENERATOR SYSTEM FOR PUMPING STATION  
  DESIGN, MANUFACTURE, SUPPLY & INSTALLATION COMMISSIONING AND MAINTENANCE OF 6 NOS. 12,000 Cu.M/hr SEA COOLING WATER PUMPS  
  CONSTRUCTION OF NEW GATHERING CENTER – GC-25  
  BOILER MAKE-UP WATER TREATMENT PLANT-SOUTH SHUAIBA POWER STATION  
  DESIGN AND INSTALLATION OF INTER-REFINERY TRANSIT LINES (IRT PIPELINES)  
  DESIGN & DETAIL ENGINEERING OF PRODUCT LOADING AND UNLOADING PIPELINES AT BERTH 13, SHUAIBA PORT  
       
 
DESIGN, SUPPLY OF MATERIAL AND CONSTRUCTION OF FLOW LINES AND ASSOCIATED WORKS FOR OIL WELLS AT GC-27 AND GC-28
Client: Kuwait Oil Company
Project Value: US$ 27 Million
Duration: 1997-1999
Brief Scope of work: The project was to construct cross-country pipe lines (Flow Lines) to run crude oil from oil wells to new Gathering Centers GC-27 and GC-28.
The Scope included:
  • Survey of Pipe routes and preparation of Route Drawings
  • Design, Supply and Construction 800 km of cross-country pipelines
  • Supply of valves and fittings
  • Design and Construction of platforms and pipe support structures
  • Design and Construction of Well Hand Fencing
  • Design, Fabrication, Supply and Installation of Pipe Heaters
  • RCC
  Top
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF STEAM SYSTEM REVAMP PROJECT (SSRP) AT MINA ABDULLA REFINERY
Client: Kuwait National Petroleum Company
Project Value: US$ 23 Million
Duration: 1997-2000
Brief Scope of work: The Scope of Work was Detail Engineering, Preparation of Equipment Specification and Data Sheets, Procurement of Equipment and Materials and Construction of Plant, inclusive of the following:
  • Steam Boilers
  • Boiler Feed Water Pump
  • 11 KV Packaged Substation
  • Instrumentation & Control Systems (DCS)
  • Fire Fighting and Fire Alarm System
  • Communication System
  • Standby Generator
  • Piping System (Inch-meter 90000)
  • RCC
  • Lighting System
  • Access Road and Landscaping
  • Structural - 280 tons
Top
FUEL OIL SUPPLY PROJECT (FOSP)
Client: Kuwait National Petroleum Company
Project Value: US$ 18 Million
Duration: 1997-1999
Brief Scope of work:
 
The Project was to enhance its fuel oil supply to the Doha Power Plant of the Ministry of Electricity & Water, via pipeline to meet the higher fuel demand. The scope of the project was Design, Detail Engineering, Preparation of Equipment Specifications, procurement, Supply of Equipment & Materials, Construction, Testing and Commissioning of Fuel Oil Pumping System.
The main equipment and construction works involved were:
  • Design Engine for Pump
  • Diesel Engine-driven Pump
  • Electrical Motor-driven Pump
  • 11 KV Packaged Substation
  • Instrumentation & Control Systems
  • Fire Fighting and Fire Alarm Systems
  • Communication Systems
  • Metering System
  • Piping System
  • Control Room Building
  • Lighting System
  • Access Road and Landscaping
Top
DESIGN, DETAIL ENGINEERING AND CONSTRUCTION OF AHMADI DEPOT AND MODERNIZATION OF SABHAN DEPOT
Client:
 
Kuwait National Petroleum Company
Local Marketing Department
Project Value: US$ 17.5 Million
Duration: 1996-1999
Brief Scope of work: The Project Was to Design and Construction a fully Automatic, unmanned, new product distribution center for KNPC at Ahmadi and modernize the existing depot at Saban to increase the efficiency of local distribution of Petroleum Products in Kuwait. The scope of work included Design, Detail Engineering, Preparation of Equipment Specification, Procurement of Equipment & Material and Construction of Depot, Inclusive of the following:
  • Control Room/Substation/Office Buildings
  • Loading & Unloading Gantry
  • Tankage
  • 11 KV Substation
  • Instrumentation & Control Systems (DCS)
  • Fire Fighting & Alarm System
  • Communication System
  • Metering System
  • Piping System
  • Cathodic Protection
  • Automation System
  • Access Road & Landscaping
  • Structural works
Top
DESIGN, MANUFACTURE, SUPPLY, INSTALLATION AND COMMISSIONING OF EMERGENCY GENERATOR SYSTEM FOR PUMPING STATION
Client: Shuaiba Area Authority
Project Value : US$ 13 Million
Duration: 1994-1997
Brief Scope of Work: The Project was to provide a 18 MW Standby Power Supply System to Shuaiba Area Authority Sea Cooling Water Pumping Plant C. The cope included design, supply , Construction and Commissioning works inclusive the following:
The main equipment and construction works involved were:
  • Diesel Engine of Generator
  • 2 Nos. 8 MW Generators
  • Electric Motor driven pump
  • 11 KV Switch Gear
  • PLC based Control System
  • Fire Fighting and Fire Alarm Systems
  • Heat Exchangers
  • Piping System
  • Plant Building
  • RCC
  • Structural Work
     
Top
DESIGN, MANUFACTURE, SUPPLY & INSTALLATION COMMISSIONING AND MAINTENANCE OF 6 NOS. 12,000 Cu.M/hr SEA COOLING WATER PUMPS
Client: Public Authority for Industries (PAI)
Project Value: US$ 12 Million
Duration: 1994-1997
Brief Scope of work:
 
The scope consisted of Design, Supply and Construction jobs in association with the modification of the Pumping Plant of Shuaiba of Area Authority.
The main equipment and works are as follows:
  • 12000 cu.m/hr Sea Cooling Water Pumps – 6 Nos
  • Band Screen
  • Pump Motors
  • Cathodic Protection
  • Main Heater
  • Pump Chamber
  • H.V. Electric Systems
  • Instrumentation and Control System
  • Structural works
     
Top
CONSTRUCTION OF NEW GATHERING CENTER – GC-25
Client: Kuwait Oil Company/Daelim Engineering & Construction Company
Project Value: US$ 10 Million
Duration: 1998-2000
Brief Scope of Work: The work consisted of construction, testing and Commissioning of complete Underground and Aboveground Piping, including painting works for the following:
  • Manifold Area - Process Liquid Lines
  • Flare Area - Blow Down Lines
  • Fire Protection - Fire Water Lines
  • Utilities - Various Drain Lines
  • Pig Launcher Area - Export Lines
  • Brackish Water & Domestic Water Lines
  • Process Condensate & Process gas lines
  • NACE specified Fuel Gas Lines
  • Structural Erection Work of Various Shelters
  • Painting of Pipelines and Shelters
Top
BOILER MAKE-UP WATER TREATMENT PLANT-SOUTH SHUAIBA POWER STATION
Client: Ministry of Electricity & Water
Government of Kuwait
Project Value: US$ 5.1 Million
Duration: 1993-94
Brief Scope of work: Design, Supply & Construction of Boiler Make-up Water Treatment
Plant including –
  • Plant Building
  • Steel Tanks & Vessels
  • Structural Steel
  • Pumps
  • Chemical Injection Systems
  • Piping
  • PLC based Control System Installation
  • Plant Electrical System
  • Instrumentation System
  • Analyzers
Top
DESIGN AND INSTALLATION OF INTER-REFINERY TRANSIT LINES (IRT PIPELINES)
Client:  Kuwait National Petroleum Company/Flour International Limited
Project Value: US$ 3.75 Million
Duration: 1996
Brief Scope of work: The Project was to construct an inter-Refinery Cross-country Transit Lines 24” dia between Shuaiba Refinery and Mina Al-Ahmadi Refinery for transfer of various petroleum products. The scope of work included Field Survey, Design & Detail Engineering, Supply of partial materials Construction of 24” cross-country pipeline and associated works inclusive of:
  • Pipeline 18” - 24” - 8 Kms
  • Motor operated Valves
  • Cathodic Protection
  • Pipe Rack & Platforms
  • Electrical System
  • Instrumentation System
  • Valves Pits
  • Structural Works
  • RCC
Top
DESIGN & DETAIL ENGINEERING OF PRODUCT LOADING AND UNLOADING PIPELINES AT BERTH 13, SHUAIBA PORT
Client: EQUATE Petrochemical Complex/ Flour International Limited
Project Value: US$ 3.4 Million
Duration: 1997
Brief Scope of Work: The Project was to design and construct all facilities for loading and unloading of various petroleum products for the Equate Petrochemical Plant to the ships and vice versa. The scope of work consisted of Design, Detail Engineering, Supply of all materials (except piping) and construction of the following facilities:
 